External review urges 29 reforms at Bane NOR after Dovrebanen delay to 2032
Commissioned after the Dovrebanen double track to Hamar slipped to 2032, a Ministry of Transport review criticises weak internal compliance and late risk warnings at Bane NOR. Transport Minister Kamzy Gunaratnam has asked Bane NOR to set up a follow-up system.
- Coverage
- Norway
- Verification
- ✓ 4 sources checked ↓
On 19 November, the Ministry of Transport (Samferdselsdepartementet) published an external review recommending 29 reforms to how Bane NOR, Norway’s state railway infrastructure manager, plans and controls major rail projects. Commissioned after the double-track upgrade towards Hamar on Dovrebanen slipped five years to 2032, the report by Implement Consulting Group and Marstrand concludes that Norway’s rail governance systems are largely in place, but compliance inside Bane NOR must improve.
The 14-kilometre Sørli–Åkersvika section through Stange in Innlandet was originally due to open in December 2027 to allow two regional express trains an hour between Oslo and Hamar. Under a revised agreement signed on 22 June 2026, opening is now set for 2032, with timetable improvements delayed to 2033. According to the review, Sørli–Åkersvika’s cost forecast has reached NOK 12.0 billion (in 2026 prices), up from a 2022 fixed price of NOK 8.8 billion and a parliamentary cost ceiling of NOK 9.5 billion, partly after work across the Åkersvika wetland was shifted into the project.
No final crossing design or revised cost ceiling has yet been approved. Bane NOR has paused work north of Ottestad while redesigning the route across the internationally protected Åkersvika Ramsar wetland reserve, where a 200-year flood standard, acid-forming alum shale and radioactive peat masses—described by Bane NOR as harmless to humans but requiring special disposal—complicate construction. Bane NOR says the new Stange station is still scheduled to open with two tracks in 2027, while the linked Hamar station upgrade is also pushed back towards 2032–2033.
Wider rail lessons and 29 measures
Examining Trønderbanen, Vestfoldbanen and the national ERTMS digital signalling rollout, the consultants found recurring problems: immature plans, late risk warnings to Jernbanedirektoratet (the Norwegian Railway Directorate), and previous review recommendations closed on paper without changing practice. On Trønderbanen, forecast costs rose from roughly NOK 2.0 billion to NOK 5.6 billion after eight extra projects were added and signalling plans shifted. On Vestfoldbanen, ERTMS delays pushed the Nykirke–Barkåker double track from autumn 2024 to November 2026.
The 29 proposals focus on stronger project planning, better internal compliance and clearer information flow between Bane NOR and Jernbanedirektoratet. They include mandatory schedule-uncertainty analyses, moving external quality assurance to Bane NOR’s board level, and splitting ERTMS into smaller phased packages for Stortinget, Norway’s parliament, to approve.
Official responses
Transport Minister Kamzy Gunaratnam said she has asked Bane NOR to establish a follow-up system. “The measures Bane NOR introduces must take effect so that money is used better, and so that it is noticed on the tracks and on the trains,” she said (translated from Norwegian).
Bane NOR chair Per Sanderud said the agency takes the findings seriously and has strengthened board oversight of its project portfolio. Chief executive Agnete Johnsgaard-Lewis pointed to a new project model now being rolled out to clarify roles and handle risk faster.
In Norway’s rail system, Stortinget sets budgets and cost ceilings for projects above NOK 1 billion, the ministry sets policy, Jernbanedirektoratet buys services and infrastructure packages, and Bane NOR builds and operates the tracks. A joint national plan for renewing railway signalling is due to the ministry by 15 March 2027.
Fact-checked sources
✓ 4 sources verified
Produced by our AI-assisted transport & weather desk and checked claim-by-claim against these public sources before publication.
- Samferdselsdepartementet, press release on rail project governance review (19 November 2026)regjeringen.no ↗
- Implement Consulting Group and Marstrand AS, external review report (November 2026, PDF)regjeringen.no ↗
- Bane NOR, response to rail investment review (19 November 2026)banenor.no ↗